Audits
Audit programme
Internal audits of the QMS, customers auditing us, and us auditing our suppliers — with findings carried through to close-out or an NCR.
Due next 60 days
5
In progress
1
Open findings
2
0 past due
Completed, 12 months
8
Supplier approvals due
1
within 30 days
Drag an audit to move it. It can't be closed while it has open findings.
Planned1
Boeing Defence Australia – E-7A supplier assessment
Customer
Boeing Defence Australia · 05 Nov 2026 · BDA Supplier Quality
In progress1
Virgin Australia supplier audit – placards & markings
Customer
Virgin Australia Airlines Pty Ltd · 07 Oct 2026 · Virgin Australia Supplier Quality
Findings open0
Drop here
Closed1
Northrop Grumman – KC-30A supplier surveillance
Customer
Northrop Grumman Australia Pty Ltd · 05 July 2026 · NGA Supplier Quality
Programme · Customer
| Date | Audit | Type | Auditing / audited | Lead | Findings | Status |
|---|---|---|---|---|---|---|
| 05 Nov 2026 | AUD-26-012Boeing Defence Australia – E-7A supplier assessment | Customer | Boeing Defence AustraliaOn-site | BDA Supplier Quality | 0 | Planned |
| 07 Oct 2026overdue | AUD-26-008Virgin Australia supplier audit – placards & markings | Customer | Virgin Australia Airlines Pty LtdOn-site | Virgin Australia Supplier Quality | 0 | In progress |
| 05 July 2026 | AUD-26-006Northrop Grumman – KC-30A supplier surveillance | Customer | Northrop Grumman Australia Pty LtdRemote | NGA Supplier Quality | 0 | ClosedSatisfactory |
| 12 Mar 2026 | AUD-26-002Jetstar supplier quality audit | Customer | Jetstar Airways Pty LtdOn-site | Jetstar Supplier Quality (Priya Raman) | 1 | ClosedSatisfactory with findings |